Dongying Hydrogenation Reactor Transport
Case details
Cargo Specification:
Hydrogenation Reactor: ?4.73*32.5M,957T, 2 units;
Hydrogenation Reactor: ?4.73*22.5M,655T, 1 unit
Project time:2016.05-2016.11
Logistics Route: Shandong HHRC- Shandong Jincheng Petrochemical Group
project
Applied Equipment:
Mercedes Benz 4160+Goldhofer 4 colums 27 axles+Mercedes Benzs2354
Mission Difficulties:
Bridge survey, force calculation, set up bridge enforcement plan and equipment loading plan, apply for administration approval, and the execution of bride enforcement;
As height limited, slide is the only way for passing several bridges, we made special sliding plan and equipment for such heavy cargo;
The mass axle trailers and gantry crane were applied in the project, complex coordination for the whole equipment and related work forces.
Live picture